July 11th 2024

Street Task Estimated Start Estimated Finish Approximate Duration
Main Street Base Prep Monday, July 08, 2024 Wednesday, July 17, 2024 7 days
Paving Wednesday, July 17, 2024 Saturday, July 20, 2024 4 days
Park Ave Paving Monday, July 22, 2024 Monday, July 22, 2024 1 day
Christie Street Base Prep Tuesday, July 09, 2024 Wednesday, July 24, 2024 6 days
Paving Thursday, July 25, 2024 Thursday, July 25, 2024 1 day
Cook Paving Friday, July 26, 2024 Saturday, July 27, 2024 2 days

All scheduled times are subject to change

Roads to be Paved as part of Project

Phase 1 - 2024 - June - August

  • Collison Ave
  • Cook St
  • Hodges Ave
  • Main St
  • McDonald St
  • McLeod St
  • Millard St
  • Northwest Dr
  • Orr St
  • Penna Rd
  • Trumpeter Dr
  • Wallace St

Phase 2 - 2025 - May - September

  • Alder Cres
  • Balsam Cres
  • Burgess Ave
  • Cedar Cres
  • Charles St
  • Christie St
  • Daisy St
  • Dogwood Cres
  • Elm Cres
  • Fir Cres
  • Hemlock Cres
  • Old Beach Rd
  • Maple Cres
  • McBride St
  • Mallard Cres
  • Park Dr
  • Pine Cres
  • Pintail Cres
  • Spruce Cres
  • Swan Cres
  • Tahayghen Drive
  • Teal Blvd
  • Wandelville St
  • Widgeon Blvd
  • Wilson St

Contact Information

Terus Construction

Warren Beal, Area Manager - 250-627-9815

Chad Bergman, Project Coordinator/Superintendent - 250-624-1126

Twyla Chamberlain, Contract Administrator - 778-884-0760

Village of Masset

Sylvan Daugert, Public Works - 250-626-3616

Rob Shearer, Contract Administrator - 250-667-6347

Joshua Humphries, CAO - 250-626-3995